MS-Project users whom would normally deal with multiple predecessors and successors of an activity will surely appreciate the new feature in MS-Project 07. Being able to get an insight of what really driving an activity will tremendously shorten troubleshooting process. Here's how to enable it.

Step1 : Go to Project ->Task Drivers
Step2 : Click on any task